This project consists of the removal and replacement of a portion of the existing double-layer built-up roofing system with EPDM cover at Whippany Park High School, including all flashings, trim, associated work, etc. The new roof system will be a built up roof system with a modified bituminous cap sheet, set in hot asphalt. Approximate square footage is as follows (note that this is for informational purposes only, contractor shall prepare their own quantity take-offs and estimate):
Base Bid 200 Wing: 18,400 s.f. approx.
Alternate Bid 100 Wing: 7,100 s.f. approx.